We remain on schedule for Phase 1 & 2 to be complete by the end of March 2025 – works are progressing well, the upgrade to Sand Martins remains exciting for members, staff and the local community. Our contractor, Kingerlee remain on course as per the project plan, Click Here to familarise yourself with the plan for Phase 1 & 2.
Click here to view our site plan showing the areas that will be under construction during Phase 1 & 2.
A high-level overview of milestones and project timescales the club and Kingerlee are working to are as follows;
- June – Site set up (Site office and Plant delivery). COMPLETE
- Mid-June – New Greenkeepers site clearance & Commencement (LHS 2nd Hole). COMPLETE
- Mid-June to August – Temporary car park construction. COMPLETE
- August to January 2025 – Main car park works. ON-GOING
- September to March 2025 – New road works into car parks, associated landscaping and pond enhancement. NOT STARTED
- TBC – substation works.
- March / April 2025 – Completion of all areas (Phase 1 & 2)
Kind regards
Matthew Short
General Manager